City Projects

Slurry Seal Application

Beginning Monday, September 30, through Friday, October 4, slurry seal will be applied to the highlighted streets on the maps below. Please follow the signed directions and flaggers to prevent any slurry seal damage to personal property. Thank you for your cooperation as we work to keep Midway’s streets in good condition.

Please direct any questions to the City Office at 435-654-3223

2024 Fall Road Improvements

Road improvement projects will begin in August 2024 in the following order:

100 East-Completed

200 East-Completed

Farm Road-In progress

Burgi Hill Park Utility Lines and Trail.

Updates will be posted as they become available.

  1. Farm Road: This project will begin after the 200 East project is completed. This project will include the installation of a new 8 inch water line, including new water meter components, a 8 inch main sewer line, with new sewer lateral to the property line and a new asphalt roadway surface.
  2. Burgi Hill Park Utility Line and Trail: This will be the final project and will begin upon completion of Farm Road. This project will replace an existing 8 inch utility line with a 10 inch line. The existing line is under the existing asphalt trail on the west side of the park. As the work begins this section of the trail will be closed. At completion of the project there will be a new utility line and a new trail on the west side of the park.

We appreciate your patience as we work to complete these needed upgrades to our infrastructure. If you have questions please feel free to contact the City Offices.